Arizona Permit Timeline Estimator

Estimate review time for a new-home permit in Yuma County and other Arizona jurisdictions, then add build time.

Review
Sourced

2019 source. 2019 compilation of the county time-frame table. Confirm with the department.

Sourced
Editable assumption

Between 1 and 4.

Use paid expedited review (where offered)Sourced

Uses the published expedited days for this jurisdiction.

Septic / environmental review neededEditable assumption

Adds 15 business days.

Variance or other zoning approval neededEditable assumption

Adds 45 business days.

Your timeline
Editable assumption
calendar days

Between 0 and 90.

Editable assumption
business days

Between 0 and 30.

Editable assumption
Build clock
Sourced
Sourced
months

Between 3 and 36.

Editable assumption
%

Between 0 and 50.

Submittal to permit in hand

63 days

About Dec 20, 2026 · move-in window Oct 19, 2027 to Feb 3, 2028

Agency review time
49 days
Your correction time
10 days
Submittal to completion
419 days (13.8 months)
Published overall time frame
35 business days for a single review. 40 business days when more than one review is needed.
Timeline
ItemAmount
Agency review49 days
Your correction time10 days
Extra reviews0 days
Issuance4 days
Build356 days

Results link:

With the defaults (Yuma County, custom plan, 2 review cycles, 10-day turnaround, hired contractor), agency time is (5 + 15 + 15) business days times 1.4 = 49 days. You add 10 days and issuance adds 4, so it is about 63 days to permit. Building at 11.7 months adds about 356 days, for about 419 days in total (about 13.8 months). The completion window is about days 366 to 473. The same inputs give about 30 days to permit in the City of Yuma, 49 in Wellton, 74 in Phoenix, and 49 in Mesa.

How this is calculated
conv        = {bd: 7/5, wd4: 7/4, cd: 1}[unit]
first, re   = (plan_type == "standard" and a standard track exists) ? standard track : custom track
if expedited and the jurisdiction publishes expedited days: first, re = expedited track

agency_cal    = (admin + first + (review_cycles - 1) * re) * conv
applicant_cal = (review_cycles - 1) * applicant_days
extras_cal    = ((septic_review ? 15 : 0) + (zoning_review ? 45 : 0)) * 7/5
issue_cal     = issuance_bd * 7/5

days_to_permit = agency_cal + applicant_cal + extras_cal + issue_cal
build_days     = build_months * 30.44
co_early       = days_to_permit + build_days * (1 - build_spread_pct/100)
co_late        = days_to_permit + build_days * (1 + build_spread_pct/100)
total_days     = days_to_permit + build_days

permit_date = submittal_date + days_to_permit
co_window   = submittal_date + co_early through submittal_date + co_late

Business days (bd) convert at 7/5. Mesa's Monday-Thursday week (wd4) converts at 7/4. Phoenix calendar days stay as calendar days. Holidays are ignored.
Septic adds 15 business days and zoning adds 45 business days. Both adders are assumptions.
Where a jurisdiction has no published standard-plan track, the custom schedule is used.
Old schedules are labeled with their source year. Confirm those with the department.

Default values and sources

Sources last verified: 2026-10-18.
DefaultValueStatusSourceNotes
Yuma County, Yuma, Wellton, San Luis, SomertonSee jurisdiction tableSourcedLand Development Coordination time frames, 2019 compilation2019 compilation of each jurisdiction's A.R.S. § 9-835 / § 11-1605 tables. City of Yuma's schedule inside it is revised 2017. Dated. Confirm with the department.
City of Yuma residential review5 work days, in generalSourcedCity of Yuma, Plan ReviewCurrent city page. The detailed 1/5/5 schedule is the 2017 table.
Phoenix first-review average32 calendar days (Sept 2026)SourcedCity of Phoenix plan review turnaround, September 2026Custom and standard plans: goal 30, average 32 calendar days. Plot plans: goal 5, average 4. Re-check quarterly.
Phoenix posted time frame10 admin + 60 substantive calendar daysSourcedCity of Phoenix license time frames (A.R.S. 9-835)Substantive time covers the first review plus one subsequent review. The 28-day re-review used here is an assumption: 60 minus the 32-day average.
Pima County review5 / 3 business daysSourcedPima County review turnaround times5 business days up to 20,000 sq ft, 3 on re-review, 3 for sites off model plans.
Tucson residential new dwelling10 business daysSourcedCity of Tucson permit review lanesFast lane, 10 business days. Initialization up to 3. Re-review is not published, so it matches the first review (assumption).
Mesa residential review10 working days (Mon-Thu)SourcedCity of Mesa residential constructionSame for later reviews. Expedited review is 5 days for a fee.
Chandler custom home20 working days per reviewSourcedCity of Chandler development services time framesStandard-plan permit is 10 working days. The week is not defined, so Monday-Friday is an assumption.
Gilbert single-family review12 / 8 working daysSourcedTown of Gilbert project review time framesStandardized plans are 3 / 3. The week is not defined, so Monday-Friday is an assumption.
Scottsdale residential review7 admin + 15 substantive business daysSourcedCity of Scottsdale residential plan reviewRe-review is not published, so it matches the first substantive review (assumption).
Glendale custom home15 / 13 business daysSourcedCity of Glendale plan review targets, effective Jan 29, 20182018 source, not on the city site. Confirm with the department. Intake is 1 business day. Expedited review is half time at a 300% fee.
Posted time-frame statuteCities and counties must post framesSourcedA.R.S. § 9-835 and § 11-1605County statute: https://www.azleg.gov/ars/11/01605.htm
Permit to completion11.7 / 14.3 / 7.4 monthsSourcedCensus Survey of Construction via NAHB, 2025Hired contractor 11.7 months, owner-built 14.3, built for sale 7.4. Mountain division average 9.1 months across types.
Your turnaround per correction10 calendar daysEditable assumptionNo public source verifiedTime for your designer to answer comments and resubmit.
Approval to permit in hand3 business daysEditable assumptionNo public source verifiedPay fees and turn in contractor documents.
Septic or environmental review15 business daysEditable assumptionNo public source verifiedAdded only when the toggle is on.
Variance or zoning approval45 business daysEditable assumptionNo single statewide figure verifiedSet from published variance frames of 35 business days (San Luis) and 45 (Somerton) in the 2019 compilation. Added only when the toggle is on.
Build-time uncertainty15% either wayEditable assumptionNo public source verifiedWidth of the completion window.
Planned submittal dateThe day you open the pageEditable assumptionNo public source verifiedUsed only to show calendar dates.

Sources last verified: 2026-10-18. Re-verify every source at least yearly.

Jurisdiction time frames

Business days convert to calendar days at 7/5. Mesa's Monday-Thursday week converts at 7/4. Phoenix figures are already calendar days. Schedules from 2017, 2018, or 2019 are labeled with that source year. Confirm them with the department. Phoenix publishes monthly, so re-check its figures quarterly.

Published review days used by this estimator
JurisdictionSource yearUnitAdminFirst reviewRe-reviewNotes
Yuma County (unincorporated)2019Business days515152019 compilation of the county time-frame table. Confirm with the department.
City of Yuma2017Business days1552017 schedule, reprinted in a 2019 compilation. The city page still says residential reviews are generally 5 work days. Confirm with the department.
Town of Wellton2019Business days510102019 compilation. Confirm with the department.
City of San Luis2019Business days1552019 compilation. Confirm with the department.
City of Somerton2019Business days1552019 compilation. Confirm with the department.
City of Phoenix2026Calendar days03228September 2026 report: custom and standard plans averaged 32 calendar days (goal 30). The 28-day re-review is an assumption: the 60-day substantive frame minus that 32-day average.
Pima County (unincorporated)Current pageBusiness days053Posted turnaround: 5 business days up to 20,000 sq ft, 3 business days on re-review.
City of TucsonCurrent pageBusiness days31010Residential new dwelling is on the fast lane at 10 business days. Initialization can take up to 3. Re-review is not published, so it is set equal to the first review.
City of MesaCurrent pageMon-Thu0101010 working days on a Monday-Thursday week, including later reviews. Expedited review is 5 days for an extra fee.
City of ChandlerCurrent pageBusiness days02020Custom home is 20 working days per review. The city does not define the week, so this tool counts Monday-Friday. That week length is an assumption.
Town of GilbertCurrent pageBusiness days0128Single-family custom or standard is 12 and 8 working days. The town does not define the week, so this tool counts Monday-Friday. That week length is an assumption.
City of ScottsdaleCurrent pageBusiness days71515Single-family admin review is 7 business days and substantive review is 15. Re-review is not published, so it is set equal to the first review.
City of Glendale2018Business days115132018 target turnaround, not hosted on the city site. Confirm with the department. Expedited review is half time at a 300% fee.

How the timeline is built

What this estimator measures

Getting a new house permitted and built in Arizona has two clocks. The permit clock runs from the day you submit plans until the permit is in your hand. The build clock runs from permit to final inspection and certificate of occupancy. This tool estimates both, so you can plan rent, rate locks, and lot carry costs around a realistic date instead of a hopeful one.

Where the review numbers come from

Arizona law requires cities (A.R.S. § 9-835) and counties (A.R.S. § 11-1605) to publish how long each kind of permit review takes, split into an administrative (completeness) review and a substantive (technical) review. We collected those tables for unincorporated Yuma County, the City of Yuma, Wellton, San Luis, Somerton, and the larger cities: Phoenix, Tucson, Pima County, Mesa, Chandler, Gilbert, Scottsdale, and Glendale. Each row in the table links to its source. Some are recent monthly reports. Others are older posted schedules, flagged by the year on the source.

Departments count time differently. Most count business days, Phoenix reports calendar days, and Mesa counts a Monday-Thursday working week. The tool converts everything to calendar days so the jurisdictions can be compared directly.

The part you control: correction rounds

Few custom-home plan sets are approved on the first pass. Each correction round adds the agency's re-review time plus the days your designer takes to respond. In fast jurisdictions, your own turnaround can take longer than the agency's review. Complete submittals, a designer who answers comments within a week, and a standard plan where one is available are the biggest ways to shorten the permit clock.

Extra reviews on rural lots

Rural lots in Yuma County often need more than a building review: septic or environmental programs, flood control, and sometimes a well permit. A variance or zoning approval can add more than a month, because it involves public notice. Turn these on if they apply. The added days are placeholders, so ask the department for current figures.

The build clock

Census data shows homes built by hired contractors took about 11.7 months from permit authorization to completion in 2025. Owner-built homes took about 14.3 months, and homes built for sale about 7.4. The 15% window reflects weather, trade availability, and inspection scheduling.

Connect it to your budget

Time costs money. Enter the months to permit as the pre-build period in the Lot Carry Cost Calculator, and the total months as the waiting period in the Build vs Buy Calculator, so property tax, interest, and rent are counted for the full stretch.

Use it as a planning range

Published review times are targets, and departments note they can slip when workloads are heavy. Call the building department before you set dates with contractors or lenders. Phoenix publishes monthly, so re-check its figures quarterly.

You can estimate what the house will cost, price the months you'll be waiting, or add the wait to build vs buy. Related writing: Arizona permitting guides.

Questions

How long does it take to get a building permit for a new home in Yuma County?

For unincorporated Yuma County, the county's posted schedule allows 35 business days for a residential permit with a single review cycle. That's 5 days of administrative review and 15 of substantive review, plus a second round of 5 and 10 days. With one correction round and 10 days for your own changes, this tool estimates about 63 calendar days from submittal to permit in hand.

How long does City of Yuma plan review take for a house?

The City of Yuma says residential plan reviews generally take 5 work days. Its posted schedule for a new residential building is 1 day for completeness, 5 for the first review, and 5 for a second review if needed, 11 business days in all. With one correction round, the tool estimates about a month from submittal to permit.

How long does Phoenix take to review new single-family home plans?

Phoenix's September 2026 report shows an average of 32 calendar days for the first review of custom and standard new-home plans, against a 30-day goal. Its posted state-law time frame is 10 administrative days plus 60 substantive days. Homes built from an already-approved standard plan go through plot-plan review, which averaged 4 days.

How long does it take to build a house after the permit is issued?

Census data for 2025 shows about 11.7 months from permit authorization to completion for homes built by a hired contractor. Owner-built homes took about 14.3 months, and homes built for sale about 7.4 months. The Mountain region, which includes Arizona, averaged 9.1 months across all home types.

Are published permit review times firm deadlines?

No. They're targets or maximum time frames, and in many departments the review clock pauses while they wait on your corrections. Phoenix and Pima County both note that turnaround times can vary with workload. Confirm current times with the department before you schedule.

Educational estimate only. Review times come from schedules each jurisdiction has published, some of which are several years old. Confirm current times with the building department. Nothing here promises any approval or date.